As promised here is an update on the progress of the shed aka ManCave.
The slab went down early last week, we also opted to get a 6mx6m pad put out the front of it to allow for additional parking.
Here is the finished product:
and then came the rain, we had 4 days of pretty heavy falls which meant the construction of the shed was delayed for a bit, but there was a bit of a break in the weather on Saturday meaning that the guys could come a do a couple of hours prep work, then come Monday things were full steam ahead with the frame being laid out and by the end of the day the outside frame and 2 walls were up.
As you can see in the pics we need to really concentrate on sorting out the drainage once the shed is complete due to the amount of rain we have been receiving.
The rest of the walls went up along with some of the roof on Tuesday, we opted for skylights to help with providing some natural light since there are no windows.
Today means that the final bits should be going up and we will be able to finally start using the shed, yipee!