We are pleased to report that work has started on site, check out the piccies below:
The site was cut on Monday and the hole for the HSTP was due to be done on Friday but due to recent rain it was too wet, so that has now been put off till Monday. With any luck this will quickly be followed by the plumbing/drainage and the slab later in the week.
We've been told that the frame should be ready to got the following week, yay!
At the moment the end of contract date is 28th November and they are currently building 4 weeks ahead of schedule, so it looks like we are going to have to enquire about extending the rental lease for at least a month.