Not alot of progress to report this week, we were hoping that the roof would have been completed or at least started, but our trip out to the block confirmed that the bracing and some fascia work around the exposed roof trusses had been done ready for the roof to go on along with the Kwila posts in the alfresco/outdoor area. So some progress, just not quite as much as we wanted.
The scaffolding has also gone up all around the house ready for the next stage.
| The kwila posts in the outdoor areas |
| Back view |
| Exposed roof trusses |
We also noticed that there was plywood bracing put up on both sides of the frame on the walls between the study and home theatre and the home theatre and the lounge which we'll need to speak with the Site Supervisor about as all of these walls are meant to have acoustic insulation between them, especially important in the Home Theatre area, so it looks like they will have to pull the plywood down to put the insulation in.